7. The electrical power system of a centre must be tested every 3 months, with the electrical load of equipment necessary for its operations, to ensure that operations may in no case be interrupted.
O.C. 1611-2023, s. 7.
In force: 2024-01-01
7. The electrical power system of a centre must be tested every 3 months, with the electrical load of equipment necessary for its operations, to ensure that operations may in no case be interrupted.